Works at Tuas Terminal Phase 2

31 Jul 2020 / Singapore

The working period for works at Tuas Terminal Phase 1 has been extended. The works will now be conducted from 1 August 2020 to 31 January 2021.

According to the Maritime and Port Authority of Singapore Port Marine Notice No.051 of 2020 dated 30 July 2020, the works will be carried out 24 hours daily - including Sundays & Public Holidays - within the working area bounded by the following co-ordinates (WGS 84 Datum):
1) 01 deg. 13.323'N / 103 deg. 36.876'E
2) 01 deg. 14.507'N / 103 deg. 36.876'E
3) 01 deg. 14.507'N / 103 deg. 36.901'E
4) 01 deg. 14.289'N / 103 deg. 36.900'E
5) 01 deg. 14.289'N / 103 deg. 37.041'E
6) 01 deg. 14.398'N / 103 deg. 37.041'E
7) 01 deg. 14.398'N / 103 deg. 38.755'E
8) 01 deg. 14.344'N / 103 deg. 38.755'E
9) 01 deg. 14.344'N / 103 deg. 39.024'E
10) 01 deg. 13.670'N / 103 deg. 39.275'E
11) 01 deg. 13.486'N / 103 deg. 38.892'E
12) 01 deg. 13.486'N / 103 deg. 37.571'E
13) 01 deg. 13.296'N / 103 deg. 37.571'E
14) 01 deg. 13.296'N / 103 deg. 37.300'E
15) 01 deg. 13.193'N / 103 deg. 37.300'E
16) 01 deg. 13.193'N / 103 deg. 36.901'E
17) 01 deg. 13.323'N / 103 deg. 36.901'E

The soil investigation works will entail seabed surface sampling and marine cone penetration test. Jack-up barges and crane barges will be used to carry out the soil investigation work. Tug boats will be used to shift jack-up barges and crane barges.

Self-Discharge Sand Carriers and Trailer Suction Hopper Dredger (TSHD) will discharge sand at the working area.

Dredging operations consist of TSHD, Cutter Suction Dredger (CSD) and grab/backhoe dredgers dredging clayey/sandy/residual soils.

The reclamation works consist of transport and discharge of materials utilising TSHD, CSD, flat top barges, hopper barges, and conveyor barges.

The work will also involve caisson installation. Safety boats will be deployed to warn other craft in the vicinity of the working area.

Craft involved in the works will exhibit the appropriate local and international day and night signals.

When in the vicinity of the working area, mariners are reminded to:
a) Keep well clear of the working area;
b) Maintain a proper lookout;
c) Proceed at a safe speed and to navigate with caution;
d) Maintain a listening watch on VHF Channel 22 (Jurong Control);
and
e) Communicate with Jurong Control for assistance, if required.