Unloading of bridge segments at West Kowloon Cultural District

03 Jun 2021 / Hong Kong

For approximately one month, unloading of bridge segments from a derrick barge will be carried out within the area bounded by straight lines joining the following co-ordinates (WGS 84 Datum) from (A) to (D) and the adjacent shoreline:
(A) 22° 18.022’N 114° 09.710’E
(B) 22° 18.002’N 114° 09.713’E
(C) 22° 17.998’N 114° 09.678’E
(D) 22° 18.020’N 114° 09.675’E

The bridge segments will be delivered to the works area by the derrick barge. One tugboat will provide assistance.

The hours of work will be from 0700 to 1900 hours. No works will be carried out on Sundays and public holidays. Vessels employed for the works will not stay in the works area outside the hours of work.

Vessels engaged in the operations will display signals as prescribed in international and local regulations.

Vessels navigating in the vicinity should proceed with caution.

(For information about operations in Hong Kong, contact GAC Hong Kong at [email protected])

Source: Government of the Hong Kong SAR Marine Department Notice No. 97/2021