Planned jetty outages

03 May 2021 / Immingham, United Kingdom

Immingham Oil Terminal (IOT) will be closed for testing, preparation, repairs and other work as follows:

IOT Berth 1

0800 to 1700 Tuesday 11 May 2021

Hose testing and ABP mooring equipment maintenance

0800 Tuesday 18 May to 1700 Thursday 20 May 2021

Painting, hose maintenance and crane gearbox routines and rope inspections

IOT Berth 2

0800 to 1700 Friday 21 May 2021

Rope inspections and ABP mooring equipment maintenance

IOT Berth 3

0800 Tuesday 4 May to 1700 Friday 7 May 2021

Loading arm 3/2 removal – this could change to w/c 10 May depending on tidal conditions

0800 Monday 24 May to 1700 Tuesday 25 May 2021

Pipework removal, gangway repairs, fire system maintenance and ABP mooring equipment maintenance

0800 Monday 9 August to 1700 Friday 13 August 2021

Loading arm 3/2 installation

0800 Wednesday 18 August to 1700 Friday 20 August 2021

Annual loading arm maintenance

Finger Pier

0800 Wednesday 26 May to 1600 Thursday 27 May 2021

Fender repairs

South Killingholme Jetty (SKJ)

To allow continued use, and until further notice, regular inspections of the white oil loading arm must be carried out. The berth needs to be unoccupied to allow crane barge access.

0800 Monday 7 June to 1700 Friday 11 June 2021

New loading arm KLA03 installation

0800 Thursday 24 June to 1700 Friday 2 July 2021

Loading arm KLA04 removal and installation of new loading arm

0800 Tuesday 13 July to 1700 Thursday 15 July 2021

Removal of loading arm KLA02 and old hydraulic powerpack

0800 Tuesday 24 August to 1700 Thursday 26 August 2021

New loading arm hydraulic powerpack relocation

Immingham Gas Jetty (full berth, LPG and white oils)

0800 Sunday 23 May to 1700 Saturday 29 May 2021

Pipework modifications, platform repairs and ABP mooring equipment maintenance

0800 Monday 24 May to 1700 28 May

Phillips 66 diving inspection

0800 Monday 16 August to 1700 Tuesday 17 August 2021

Annual loading arm maintenance

Main Transfer Line, Tank and Loading Arm Works

22” Fuel Oil Transfer Line ILI (In Line Inspection) – ILI dates to be confirmed

2 Transfer Line ILI (in line inspection) to be scheduled in September 2021

24” Fuel Oil transfer Line – under road sections to be replaced (x 2) – w/c 7 June – 27 July

B3 LA3/2 to be overhauled in 2021. Proposed dates for critical loading arm removal and installation work – see Berth 3 outages

SKJ Loading Arm Replacement (x 3) – Preparation work will continue to be scheduled ready for new loading arm installation in 2021. Proposed dates for critical loading arm removal and installation work – see SKJ outages.

Finger Pier and Terminal Supply Lines and Custody Meters

Finger Pier loading and terminal supply lines under road replacement

There are 18 lines that come in/out of the terminal through culverts under the road.

The current planned replacement programme is:

8” Ballast line from w/c 10 May

2T/L from w/c 2 August

12” Ballast line from 20 September

GO3 from w/c 3 May

Effect on the business will be communicated as lines are taken out of service.

Custody meter proving 2021 (planned 5 days duration with some disruption to Finger Pier loading)

Week commencing Monday 13 September 2021

For information about operations in the United Kingdom, contact GAC UK at [email protected]

If quoting any content from Hot Port News, please cite GAC Hot Port News as the source.