Marine works in Wan Chai Basin

27 Nov 2020 / Hong Kong

For approximately 6 months, marine works involving demolition of existing seawall and construction of harbour steps will be carried out within the area bounded by straight lines joining the following co-ordinates (WGS 84 Datum) from (A) to (B) and the adjacent shoreline:
(A) 22°17.025’N / 114°10.834’E
(B) 22°16.965’N / 114°10.857’E

The works will be carried out by one derrick lighter. One tugboat will provide assistance.

A working area of approximately 15 metres around the lighter will be established. Yellow flashing buoys fitted with yellow flashing lights will be laid to mark the positions of the anchors extending from the lighter.

The hours of work will be from 0700 to 1900 hours. No works will be carried out on Sundays and public holidays. Vessels employed for the works will stay in the works area outside the hours of work.

A silt curtain, extending from the sea surface to the seabed, will be established within the works area. The silt curtain is a large piece of netting used to contain mud and sediments. Yellow marker buoys fitted with yellow flashing lights will be laid to mark the extent of the silt curtain.

Diving operations will be carried out from time to time during the hours of work.

Vessels engaged in the operations will display signals as prescribed in international and local regulations.

Vessels navigating in the vicinity should proceed with caution and keep clear of the works area at slow speed, bearing in mind there are divers working in the works area.

(For information about operations in Hong Kong, contact GAC Hong Kong at [email protected])

Source: Government of the Hong Kong SAR Marine Department Notice No.169/2020