Jetty strengthening at Shallow Water Berth

05 Mar 2025 / Jawaharlal Nehru Port, India

The first phase of civil work to upgrade permissible displacement at the Shallow Water Berth from 32,500 MT to 45,000 MT has been completed.

Work on the second phase has commenced towards the north side of the jetty. During this phase, tentatively expected to be completed by mid-April, vessels up to 197 metres in length can be accommodated.