You are currently on GAC Worldwide website.
Unit OT 18-35, Level 18, Central Park Towers, Dubai International Financial Centre, Dubai, P.O. Box 18006, United Arab Emirates
16200 Central Green Blvd
GAC Regional Office, Asia Pacific 78 Shenton Way, #29-01
Group Vice President, Asia Pacific & Indian Subcontinent
Unit OT 18-35, Level 18, Central Park Towers, Dubai International Financial Centre, Dubai, P.O. Box 18006, United Arab Emirates
Unit OT 18-35, Level 18, Central Park Towers, Dubai International Financial Centre, Dubai, P.O. Box 18006, United Arab Emirates
Leverage on our experience and expertise with integrated shipping, logistics and marine services tailored to meet your needs.
20 Jul 2022 / Singapore
The working period for the installation of a jetty and floating pontoons East of Coney island has been revised.
According to the Maritime and Port Authority of Singapore Port Marine Notice No.047 of 2022, the work is now being conducted from 0800 to 1900 hours daily - including Sundays and Public Holidays - until 14 Jan 2023, at the following co-ordinates (WGS 84 Datum):
1 01⁰ 24.320’N / 103⁰ 55.763’E
2 01⁰ 24.378’N / 103⁰ 55.816’E
3 01⁰ 24.320’N / 103⁰ 55.880’E
4 01⁰ 24.259’N / 103⁰ 55.825’E
The installation of jetty and floating pontoons will be carried out by crane barge and supported by work barges and tug boats.
A safety boat will be deployed to warn other craft to keep clear of the area during working hours.
Craft involved in the works exhibit the appropriate local and international day and night signals.
When in the vicinity of the working area, mariners are reminded to:
a) Keep well clear and not to enter the work area;
b) Maintain a proper lookout;
c) Proceed at a safe speed and navigate with caution;
d) Maintain a listening watch on VHF Channel 21 (Sembawang Control);
and
e) Communicate with Sembawang Control for assistance, if required.
For information about operations in Singapore, contact GAC Singapore at [email protected]