Depth update

13 Feb 2024 / Marcus Hook, United States

As advised by Monroe Energy, following post-dredging dock soundings were performed at the Marcus Hook ship dock, the depth has changed. The barge dock was not dredged due to permit restriction.

The current depth at the ship dock, referenced to the MLLW datum, is changed to 40’00” (12.19 m). The terminal has a 1-foot minimum UKC requirement. The maximum allowable FW draft is 39’ 00” (11.88 m).

Th current depth at the barge dock, referenced to the MLLW datum, is 29’00”. The terminal has a 1-foot minimum UKC requirement. The maximum allowable FW draft is 28’ 00”.

For information about operations in the United States, contact GAC North America at [email protected]

If quoting any content from Hot Port News, please cite GAC Hot Port News as the source.